GENERAL INFO
Client Requirement: 
Relocating this business unit required more than a simple move. A new meeting room and print area were needed along with alterations to existing meeting rooms to form an open space.
Aesthetics
5
Ease of Installation
5
Cost
5
Performance
5
Time / 2-8 weeks
5
Project Team:
Solution:

Working closely with the main contractor and client, we helped draft a programme that allowed the client to retain their meeting rooms, etc. while the proposed works were being carried out. This took place over three weekends and the weekday nights in between.
Temporary partitions were constructed that allowed the client to retain all services throughout the duration of the works.